Design and Build Project Scheduling Applications Using the Critical Path Method

Authors

  • Muhammad Raihan Universitas Islam Negeri Sumatera Utara
  • Abdul Syahputra Sidabalok Universitas Islam Negeri Sumatera Utara

DOI:

https://doi.org/10.55537/bigint.v3i2.1255

Keywords:

Project Scheduling, Critical Path Method, Critical Path

Abstract

Effective project planning and scheduling is a crucial factor in ensuring the successful implementation of projects, especially in the construction sector. CV Kayfa Permata, a construction company, often faces challenges in managing project time and resources optimally. To overcome these challenges, this study aims to design and build a desktop/web-based project scheduling application that implements the Critical Path Method (CPM) method. The uniqueness of this application lies in its ability to automatically calculate critical paths, total project duration, as well as visualize work network diagrams, which are directly tailored to the operational needs of the local company. Different from a theoretical or simulation approach, this research produces an applicative solution that can be implemented directly in a real work environment. The application development methodology uses a waterfall approach, with stages of needs analysis, system design, implementation, and testing. The test results show that the app is able to improve the efficiency of project scheduling and simplify the decision-making process. With this application, it is hoped that the project scheduling process at CV Kayfa Permata will be more systematic, efficient, and measurable.

Downloads

Download data is not yet available.

References

Ba'Its, H. A., Arum Puspita, I., & Bay, A. F. ,(2020) “ Combination of Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) for Project Schedule Development.,” International Journal of Integrated Engineering, vol. 12, no. 3, pp. 68-75.

H. Lu, J. Zhang dan P. Li, (2021) “Random Forest Models for Construction Project Predictions,” Journal of Artificial Intelligence Research, vol. 64, pp. 255-273.

E. Wibowo dan e. al., (2023) “Implementation of CPM in Small-Medium Construction Enterprises: Challenges and Solutions.,” Proceedings of the 5th International Conference on Civil Engineering, pp. hal. 230-245.

S. A. dan e. al, (2022) “Critical Path Method Analysis for Delayed Projects: A Case Study of Infrastructure Development.,” Journal of Construction Engineering, vol. 15, no. 2, pp. 112-125.

J. Heizer dan B. Render, (2014)“ Operation Management Sustainability and Supply Chain Management,” dalam 11th Edition, Pearson.

R. K. Gupta dan S. Patel, (2020)“Resource Allocation in Critical Path Method: A Machine Learning Approach,” Automation in Construction, vol. 118.

D. Fitriani dan W. Zhang, (2021) “Web-Based Project Scheduling System with Gantt Chart Visualization,” vol. 9, pp. 45678-45689.

I. A. Kusumadarma, D. Y. I. P. Pratami dan W. Tripiawan, (2020) “ Developing Project Schedule in Telecommunication Projects Using Critical Path Method (CPM).,” International Journal of Integrated Engineering, vol. 12, no. 3, pp. 60-67.

C. B. Amarnath dan M. Swetha, (2023) “Optimization of Construction Project Scheduling Using Critical Path Method.,” International Journal of Engineering Research & Technology, vol. 12, no. 3, pp. 45-52.

Kosztyán, Z, (2019) “ T. Advanced Project Scheduling: A Systematic Literature Review,” International Journal of Project Management, vol. 32, no. 2, pp. 256-278.

H. Kerzner, (2022) Project Management: A Systems Approach to Planning, Scheduling, and Controlling, Wiley.

H. Lee dan J. Kim, (2022)“Real-Time Project Monitoring Dashboard for Agile Construction Management.,” IEEE International Conference on Industrial Informatics , pp. 1-6.

V. Jain, P. Sethi, S. Arya, R. Verma dan C. Chawla, (2020)“Project Evaluation Using Critical Path Method & Project Evaluation Review Technique.,” Wesleyan J. Res, vol. 13, pp. 1-9.

M. Lu dan H. Li, (2023) “Resource-activity critical-path method for construction planning,” Journal of Construction Engineering and Management, vol. 129, no. 4, pp. 412-420.

G. R. Rakasyiwi, B. Witjaksana dan H. T. Tjendani, (2022) “Project scheduling analysis using the critical path method—case study: subsidized house construction project in hill mulya housing Samarinda city.,” International Journal on Advanced Technology Engineering and Information System (Ijateis), , vol. 1, no. 4, pp. 73-88.

Downloads

Published

2025-08-09

How to Cite

Raihan, M., & Sidabalok, A. S. (2025). Design and Build Project Scheduling Applications Using the Critical Path Method. Bigint Computing Journal, 3(2), 91–99. https://doi.org/10.55537/bigint.v3i2.1255

Issue

Section

Article